| PROJECT: |
St. Ignace/Mackinac
Island Submarine Cable Crossing |
| COMPLETED: |
June 1988 |
| CLIENT: |
Edison Sault Electric Co.
Sault Ste. Marie, Michigan |
| SPECIFICS: |
Simultaneously installed
four each 25KV armored submarine cables. Each cable was 18,200 feet in length. Drilling
and blasting was required for trench embedment. |
|